Development of eight residential apartments at Wendens Ambo
Date of Article
Nov 02 2021
Sector
Planning & development

Keep informed

Sign up to our newsletter to receive further information and news tailored to you.

Sign up now

Carter Jonas’ Cambridge planning team were instructed by the Guster Group (a longstanding client) acting on behalf of Mill House Court Ltd to submit and manage a written representations appeal against a refusal by Uttlesford District Council to grant planning permission for the development of a block of eight residential apartments at Wendens Ambo, Saffron Walden in Essex.

Following a lengthy planning application process and a refusal based upon alleged heritage impacts, an appeal was submitted in October 2020. The appeal decision was allowed in October 2021 granting planning permission for the scheme. Following the Inspector’s assessment of appellants’ statement of case it was concluded there would be no unacceptable harm to designated heritage assets. 

Carter Jonas had also applied on behalf of the client for a full award of costs, which was subsequently allowed. In the costs decision, the Inspector concluded: ‘I consider that the Council’s case has not indicated that a thorough and balanced assessment has been undertaken…The submissions indicate a confused, confusing and inaccurate assessment which lacks the necessary rigour.’ The Inspector further stated, ‘the Council has sought to prevent and has delayed development which should reasonably have been allowed…this has incurred unnecessary expense and delay which the appellant should not have had to incur’.

The brownfield site is in a highly sustainable, high demand location, located close to Audley End railway station on the London to Cambridge line. The proposals are for a high-quality development which we look forward to coming to fruition.

planning bulletin article oct 21 wendons ambo

(Image source: Moses Cameron Williams Architects, taken from Design and Access Statement)